article · International Journal of Industrial and Operations Research · 2020
Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study
Cited by 31Open access
Abstract
The project evaluation and review technique (PERT) and critical path method (CPM) were applied in a building construction company. Different activities involved in the house construction project were described. The earliest events, latest commencement and completion of activities were determined using Forward and Backward pass computations in CPM. Critical paths were determined using both CPM and PERT. Based on the analysis, it was shown that the completion of the house project using CPM was almost the same with that of PERT such that the difference between both techniques was only one day.
Cite this paper
Orumie, U. C. (2020). Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study. International Journal of Industrial and Operations Research, 3(1). https://doi.org/10.35840/2633-8947/6504
Orumie, Ukamaka Cynthia. “Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study.” International Journal of Industrial and Operations Research, vol. 3, no. 1, 2020, https://doi.org/10.35840/2633-8947/6504.
Orumie, Ukamaka Cynthia. 2020. “Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study.” International Journal of Industrial and Operations Research 3 (1). https://doi.org/10.35840/2633-8947/6504.
Orumie, U.C. (2020) ‘Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study’, International Journal of Industrial and Operations Research, 3(1). Available at: https://doi.org/10.35840/2633-8947/6504.
@article{orumie2020implementation,
title = {{Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study}},
author = {Orumie, Ukamaka Cynthia},
journal = {International Journal of Industrial and Operations Research},
volume = {3},
number = {1},
year = {2020},
doi = {10.35840/2633-8947/6504}
}Made from the index record. Check names, capitalisation and page numbers against the paper. Need another style? AI for Research has over 10,000.
Related papers
Comparing the Effectiveness of PERT and CPM Techniques in a House Construction Project: A Case Study
Methaq Azeez Jouda, Mushtak A. K. Shiker · Journal Européen des Systèmes Automatisés · 2024
Cited by 2Open access
Applying Project Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) In Network Analysis (Evidence from The Building Practice Ltd at Badagry Local Government, Lagos)
Ilo Hammed Owolabi · International Journal of Latest Technology in Engineering Management & Applied Science · 2025
Cited by 0Open access
A PERT-CPM tutorial
H. S. Swanson, Robert E. D. Woolsey · ACM SIGMAP Bulletin · 1974
Cited by 5
Project Management Using Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT)
P. N. Ezra, Favour Elohor Egedegbe, Cynthia Ndidiamaka Nwafor et al. · INTERNATIONAL JOURNAL OF MATHEMATICS AND COMPUTER RESEARCH · 2024
Cited by 2Open access
Using the Program Evaluation and Review Technique and the Critical Path Method to Help Project Managers
Ehaimed, Esraa Tayyeh, Ghany, Mushtaq Abd Al · DOAJ (DOAJ: Directory of Open Access Journals) · 2025
Cited by 0Open access
ANALISA PERBANDINGAN WAKTU PENJADWALAN PROYEK DENGAN METODE CPM (CRITICAL PATH METHOD) DAN PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE)
Siti Abadiyah, Muhammad Ali Mu’min, Teguh Dwi Julianto · Structure (Jurnal Sipil) · 2022
Cited by 1Open access
PROJECT SCHEDULING ANALYSIS USING CPM AND PERT IN THE CONSTRUCTION OF NAKULA SHOP HOUSES
Ade Yuri Syaban Ramadhan, Caroline Taruliasih Manik, Santi Dwi Zulfa et al. · INJOSEDU: International Journal of Social and Education · 2025
Cited by 0Open access
Combination of Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) for Project Schedule Development
Hamzah Abdul Ba'its, Ika Arum Puspita, Achmad Fuad Bay · International Journal of Integrated Engineering · 2020
Cited by 15Open access